According to this post Allow Study to Change Bar Period there used to be an option in the chart settings that could be enabled to allow a study to change the time period of a chart. I'd like to request this option be re-enabled.
|
| [2025-05-04 22:55:08] |
| Sierra_Chart Engineering - Posts: 20740 |
|
This exists already. Use this function: ACSIL Interface Members - Functions: sc.SetBarPeriodParameters() This is functionality that would never be removed and never has been. Although this is a newer function for doing this. Sierra Chart Support - Engineering Level Your definitive source for support. Other responses are from users. Try to keep your questions brief and to the point. Be aware of support policy: https://www.sierrachart.com/index.php?l=PostingInformation.php#GeneralInformation For the most reliable, advanced, and zero cost futures order routing, use the Teton service: Sierra Chart Teton Futures Order Routing Date Time Of Last Edit: 2025-05-04 22:55:25
|
To post a message in this thread, you need to log in with your Sierra Chart account: