No. One way to do this is to programmatically change the timeframe of the chart bars and then when the chart is reloaded, change it back to the original timeframe. Although this will cause 2 reloads during that process.

Now it is possible to perform a full recalculation by setting sc.FlagFullRecalculate to a nonzero number.