Support Board
Date/Time: Wed, 10 Sep 2025 18:34:28 +0000
Post From: sc.GetStudyArrayFromChartUsingID
[2016-04-20 21:13:11] |
|
The index is zero based. So 16 is correct. Sounds like a calculation precedence issue. Make sure the study sets: sc.CalculationPrecedence = VERY_LOW_PREC_LEVEL And is at the end of the list of studies to be calculated. For more information, refer to: Chart Studies: Study Calculation Precedence And Related Issues Sierra Chart Support - Engineering Level Your definitive source for support. Other responses are from users. Try to keep your questions brief and to the point. Be aware of support policy: https://www.sierrachart.com/index.php?l=PostingInformation.php#GeneralInformation For the most reliable, advanced, and zero cost futures order routing, *change* to the Teton service: Sierra Chart Teton Futures Order Routing |