Post From: AMP, Denali Feed, SC order Routing LAG

[2020-11-16 03:09:17]
User320357 - Posts: 3
After the post above I saw the Sticky post: Recommendations to Improve Overall Sierra Chart Performance went through all of that (video) and have substantial improvements so far for what I have changed.

One question I have though is what would be the minimum recommended Number of Days to Calculate for the Rolling VWAP study for each of the following Time Period Length settings?

1 Day VWAP Rolling
2 Day VWAP Rolling
3 Day VWAP Rolling
5 Day VWAP Rolling

Although the 1 Day calculating time is not bad with 17ms with 10 days of calculation, the

2 Day is 1554ms
3 Day is 2152ms
5 Day is 2964ms

with Number of Days to Calculate at 10

Additionally would the best option along with any suggested days to calculate be to run these in a different chart under another instance of SC?

Thank you